lundi 29 décembre 2014

Add a certain number of days for a date field


I have one field for a permit decision date, and then I have another field for 180 days from that permit date. The permit date field has data entered, but the 180 day field I would like to calculate by adding 180 days. It is a feature class in a file GDB, and both fields are in date format (mm/dd/yyyy).


Example: Permit Field date is 7/1/2009, I would like the 180 days field to be 12/28/2009.


I am using ArcGIS 10.2.2 for Desktop.





Aucun commentaire:

Enregistrer un commentaire